UPSC CSAT 2016: Question 60

Quantitative AptitudeTime & WorkQ.60 of 80

Ram and Shyam work on a job together for four days and complete 60% of it. Ram takes leave then and Shyam works for eight more days to complete the job. How long would Ram take to complete the entire job alone ?
  1. (a)6 days
  2. (b)8 days
  3. (c)10 days
  4. (d)11 days
Show answer and explanation

Answer: (c) 10 days

Together they do 15% a day. Shyam does the last 40% in 8 days, i.e. 5% a day, so Ram does 10% a day and alone needs 10 days.