UPSC CSAT 2016: Question 76

Quantitative AptitudeTime & WorkQ.76 of 80

W can do 25% of a work in 30 days, X can do 1/4 of the work in 10 days, Y can do 40% of the work in 40 days and Z can do 1/3 of the work in 13 days. Who will complete the work first ?
  1. (a)W
  2. (b)X
  3. (c)Y
  4. (d)Z
Show answer and explanation

Answer: (d) Z

Full job times: W 120 days, X 40, Y 100, Z 39. Z finishes first.