A person X can complete 20% of work in 8 days and another person Y can complete 25% of the same work in 6 days. If they work together, in how many days will 40% of the work be completed?
  1. (a)6
  2. (b)8
  3. (c)10
  4. (d)12
Show answer and explanation

Answer: (a) 6

X does 2.5% a day and Y 256%\frac{25}{6}\% a day, together 203%\frac{20}{3}\% a day. 40% takes 40÷203=640 \div \frac{20}{3} = 6 days.