A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work is further increased by 50%?
- (a)24
- (b)21
- (c)18
- (d)15
Show answer and explanationHide answer
Answer: (d) 15
of the job takes 21 days, so the whole job takes 24 days. With the work increased by 50%, of the job remains: days.