UPSC CSAT 2021: Question 80

Quantitative AptitudeTime & WorkQ.80 of 80

A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work is further increased by 50%?
  1. (a)24
  2. (b)21
  3. (c)18
  4. (d)15
Show answer and explanation

Answer: (d) 15

78\frac{7}{8} of the job takes 21 days, so the whole job takes 24 days. With the work increased by 50%, 1.5−78=581.5 - \frac{7}{8} = \frac{5}{8} of the job remains: 58×24=15\frac{5}{8} \times 24 = 15 days.