A, B, C working independently can do a piece of work in 8, 16 and 12 days respectively. A alone works on Monday, B alone works on Tuesday, C alone works on Wednesday; A alone, again works on Thursday and so on. Consider the following statements :
1. The work will be finished on Thursday.
2. The work will be finished in 10 days.
Which of the above statements is/are correct ?
- (a)1 only
- (b)2 only
- (c)Both 1 and 2
- (d)Neither 1 nor 2
Show answer and explanationHide answer
Answer: (a) 1 only
One A–B–C cycle does . After 9 days: . Day 10 (A): . Day 11 (B) does the last .
Day 11 counted from Monday is a Thursday. So 1 is correct and 2 is not.