UPSC CSAT 2023: Question 20

Quantitative AptitudeTime & WorkQ.20 of 80

A, B, C working independently can do a piece of work in 8, 16 and 12 days respectively. A alone works on Monday, B alone works on Tuesday, C alone works on Wednesday; A alone, again works on Thursday and so on. Consider the following statements : 1. The work will be finished on Thursday. 2. The work will be finished in 10 days. Which of the above statements is/are correct ?
  1. (a)1 only
  2. (b)2 only
  3. (c)Both 1 and 2
  4. (d)Neither 1 nor 2
Show answer and explanation

Answer: (a) 1 only

One A–B–C cycle does 18+116+112=1348\frac{1}{8} + \frac{1}{16} + \frac{1}{12} = \frac{13}{48}. After 9 days: 3948\frac{39}{48}. Day 10 (A): 4548\frac{45}{48}. Day 11 (B) does the last 348=116\frac{3}{48} = \frac{1}{16}. Day 11 counted from Monday is a Thursday. So 1 is correct and 2 is not.