A certain number of men can complete a piece of work in 6k days, where k is a natural number. By what percent should the number of men be increased so that the work can be completed in 5k days?
- (a)10%
- (b)%
- (c)20%
- (d)25%
Show answer and explanationHide answer
Answer: (c) 20%
Men × days is constant, so the number of men must become times, an increase of 20%.