PIB InsightsWeek of 29 Jun – 5 Jul 2026 · Prelims · Semiconductors, Electronics manufacturing
CG SEMI's Sanand OSAT plant starts commercial production
CG SEMI's OSAT facility at Sanand, built with Renesas Electronics of Japan, became India's third semiconductor plant in commercial production in 2026, with five expected by year-end.
Source: Press Information Bureau (PIB), Government of India
Prelims:EconomicsScience & Technology
On 4 July 2026, the CG SEMI OSAT (outsourced semiconductor assembly and test) facility at Sanand, Gujarat began commercial production, becoming India's third semiconductor plant to do so this year, in the presence of the Prime Minister. Electronics and IT Minister Ashwini Vaishnaw said India has entered a new era in semiconductors; the plant went from groundbreaking to production in 27 months.
The pipeline: the first and second plants were launched on 28 February and 31 March 2026; of the 12 approved semiconductor projects, three are now producing, two more are due in the coming months, and five are expected to be running by the end of 2026. India's first semiconductor fab, at Dholera, is progressing rapidly.
The plant: its groundbreaking was on 13 March 2024, with investment of over ₹7,600 crore, and it was built with Renesas Electronics of Japan. Its chips will serve automobiles, scooters and industrial equipment in India and will be exported to Japan, the United States and Europe. Young women from several States work there as operators after specialised training in Malaysia.
The ecosystem: the Minister said 315 universities now teach semiconductor design, more than 70,000 young people have been trained in chip design, and 24 deep-tech chip design start-ups have come up.
Source