A contract on construction job specifies a penalty for delay in completion of the work beyond a certain date is as follows : ₹ 200 for the first day, ₹ 250 for the second day, ₹ 300 for the third day etc., the penalty for each succeeding day being ₹ 50 more than that of the preceding day. How much penalty should the contractor pay if he delays the work by 10 days ?
- (a)₹ 4950
- (b)₹ 4250
- (c)₹ 3600
- (d)₹ 650
Show answer and explanationHide answer
Answer: (b) ₹ 4250
The penalties form an AP: 200, 250, …, 650 for 10 days. Sum = .