UPSC CSAT 2011: Question 35

Quantitative AptitudeNumber SystemQ.35 of 80

A contract on construction job specifies a penalty for delay in completion of the work beyond a certain date is as follows : ₹ 200 for the first day, ₹ 250 for the second day, ₹ 300 for the third day etc., the penalty for each succeeding day being ₹ 50 more than that of the preceding day. How much penalty should the contractor pay if he delays the work by 10 days ?
  1. (a)₹ 4950
  2. (b)₹ 4250
  3. (c)₹ 3600
  4. (d)₹ 650
Show answer and explanation

Answer: (b) ₹ 4250

The penalties form an AP: 200, 250, …, 650 for 10 days. Sum = 102(200+650)=₹ 4,250\frac{10}{2}(200 + 650) = ₹\,4,250.